You have chosen the units, agreed the layout, and your builder has a start date. The obvious question: how long is this going to take?
Realistic timelines
Cosmetic refresh (new doors, worktops, splashback, no layout changes): 3-5 days. The existing layout stays. No plumbing or electrical changes. This is the fastest option.
Standard refit (new units, same layout, minor plumbing/electrical): 1-2 weeks. Strip the old kitchen, fit new units, reconnect plumbing and electrics, tile, and make good. Most straightforward kitchen refits fall into this category.
Full renovation with layout changes: 3-6 weeks. Moving the sink, adding an island, relocating the boiler, knocking through a wall — all of these add time. Plumbing and electrical first fix comes before the kitchen goes in. Plastering needs to dry. Multiple trades need coordinating.
Extension or structural work involved: 8-16 weeks. If the kitchen is part of a larger project — a rear extension, a knock-through into the dining room — the kitchen itself may only take two weeks, but the structural work, building control inspections, and finishing trades push the overall timeline much longer.
What makes kitchens run late
- Hidden surprises. Rotten joists under the floor, unexpected pipework routes, asbestos in old textured ceilings. You do not know until you start.
- Delivery delays. Bespoke worktops, specific tiles, and specialist appliances have lead times. If something arrives late or damaged, the whole schedule shifts.
- Changes during the project. Moving the hob to the island, adding extra sockets, choosing different tiles after the originals are ordered. Every change has a time impact.
- Trade coordination. A kitchen refit involves a builder, plumber, electrician, plasterer, tiler, and potentially a gas engineer. If one trade is delayed, it cascades.
