The job is nearly finished. The kitchen looks great. Then your builder hands you a bill that is £4,000 more than the price you agreed. "Materials went up." "The plumbing was more complicated than I thought." "You asked for those extra shelves, remember?"
This happens more often than it should. It is one of the most common disputes in domestic building work, and it almost always comes down to one thing: what was actually agreed, and whether it was a quote or an estimate.
Quote vs estimate: the legal difference
This distinction matters because it determines your rights.
A quote is a fixed price for a defined scope of work. It is legally binding. Once you accept a quote, the builder must complete the work for that price. If the job costs them more than they expected — materials go up, the work takes longer — that is their risk, not yours. They cannot come back and charge more unless the scope of work changes.
An estimate is an educated guess at what the work might cost. It is not fixed. The final bill can be higher or lower. However, it should be within a reasonable range of the estimate. If the builder estimated £8,000 and the final bill is £9,000, that may be reasonable. If it is £14,000 with no clear explanation, you have grounds to challenge it.
The first thing to check: did you receive a quote or an estimate? Look at the original document. If it says "quote" or "quotation," the price is fixed. If it says "estimate" or "approximate cost," it is a guide. For a detailed explanation of the difference, see our guide on quote vs estimate: which protects you.
What the law says
Under the Consumer Rights Act 2015, services provided to you must be carried out with reasonable care and skill. If you hired a tradesperson to do a job for a quoted price, and they are now demanding more without a legitimate reason, that is a breach of the agreement.
The key question is whether the scope changed. If you asked for extras during the job — a different tile, additional sockets, a bigger shower — those are variations. The builder is entitled to charge for them. But variations should be agreed in writing before the work is done, not presented as a surprise on the final bill.
If the builder is charging more because they underestimated the work — they did not account for the pipework being complicated, or the plastering taking longer — that is their problem, not yours. A quote means the builder assessed the work and committed to a price. That commitment stands.
